This is the public portal for all IBM Z Hardware and Operating System related offerings. To view all of your ideas submitted to IBM, create and manage groups of Ideas, or create an idea explicitly set to be either visible by all (public) or visible only to you and IBM (private), use the IBM Unified Ideas Portal (https://ideas.ibm.com).
We invite you to shape the future of IBM, including product roadmaps, by submitting ideas that matter to you the most. Here's how it works:
Start by searching and reviewing ideas and requests to enhance a product or service. Take a look at ideas others have posted, and add a comment, vote, or subscribe to updates on them if they matter to you. If you can't find what you are looking for,
Post an idea.
Get feedback from the IBM team and other customers to refine your idea.
Follow the idea through the IBM Ideas process.
Welcome to the IBM Ideas Portal (https://www.ibm.com/ideas) - Use this site to find out additional information and details about the IBM Ideas process and statuses.
IBM Unified Ideas Portal (https://ideas.ibm.com) - Use this site to view all of your ideas, create new ideas for any IBM product, or search for ideas across all of IBM.
ideasibm@us.ibm.com - Use this email to suggest enhancements to the Ideas process or request help from IBM for submitting your Ideas.
While planing to upgrade z14 GA1 to GA2 driver, the customer asks IBM to prepare guaranteed contingency revert plan in the case of GA2 driver causes the customer's production system failure. Unlike MCL apply, GA2 driver upgrade includs lots of new functions and pre PTFs, CFCC level change, so it is such a big event for the customer. As we contacted to Z AP PE team to guide GA2 to GA1 revert plan but the answer was "No support for downgrading driver and if the failure occurs, PE will try to fix it". However the customer will never accept such answer because they cannot estimate how long time they need to stop their system until PE fix a failure. The client needs to plan a detailed time schedule for GA2 driver upgrade and it must be included a contingency plan which is detailed and clear how long required to return their system to normal operation. So the customer desires IBM to provide GA2 to GA1 downgrade option.
Idea priority | Urgent |
By clicking the "Post Comment" or "Submit Idea" button, you are agreeing to the IBM Ideas Portal Terms of Use.
Do not place IBM confidential, company confidential, or personal information into any field.
Thank you for your feedback. IBM Z has been moving to a continuous delivery for FW updates, which allows smaller incremental FW updates rather than one larger GA2 driver change. z15 is the first family generation to take advantage of this approach. The HMC functions have also been updated to include more granularity and timing control for MCLs. Please let us know if this does not address planning needs as desired.